Individual skill

sprint-plan

Capacity-gated sprint planning — runs capacity math, carry-over check, and a definition-of-ready gate before committing scope. Usage: /sprint-plan <goal> [capacity]

.gemini/skills/sprint-plan/SKILL.md

Read pinned source

Source commit 8f082544116fc0d014188e521ca40304cdfc86b0

What was checked

Matches the observed repository HEAD
Yes
Scanner rules are current
Yes
Repository scan complete
No
Skill scan complete
No
Observed behavior
Network or broad shell
Last checked
Nov 10, 2026

These are observations at the recorded commit, not a guarantee of safety. Review the source before running it.

Install this skill

Choose an agent in your Stack or copy a command below. Commands fetch the pinned commit and copy only this skill directory. Existing destinations are refused. Copying a command does not install anything.

An install command is unavailable: current rules, complete repository and skill scans, an eligible behavior level and a permitted license are required.

Repository context

Repository stars (not skill ratings)
29,645
Repository last updated
Nov 11, 2026
License
MIT

Observed agent integration: gemini-cli

Files and excerpt

File metadata and permitted, redacted excerpts come from the recorded scan. Source links are pinned to that commit.

Browse files
Read excerpt

# /sprint-plan

Create a sprint plan for `$ARGUMENTS` with explicit capacity math, a carry-over check, and a definition-of-ready gate. The first token(s) of `$ARGUMENTS` are the sprint goal; a trailing number is treated as team capacity (story points or person-days). If no capacity is given, compute it in Phase 1 — never invent it.

## Usage

```bash
/sprint-plan <goal> [capacity]
# e.g. /sprint-plan "Checkout v2 ready for beta" 34
```

## Phase 1 — Capacity Math (do the arithmetic, show it)

1. **Raw capacity** = team size × working days in sprint × focus factor (default 0.7; ask if unknown)