sprint-plan
Capacity-gated sprint planning — runs capacity math, carry-over check, and a definition-of-ready gate before committing scope. Usage: /sprint-plan <goal> [capacity]
.gemini/skills/sprint-plan/SKILL.md
Source commit 8f082544116fc0d014188e521ca40304cdfc86b0
What was checked
- Matches the observed repository HEAD
- Yes
- Scanner rules are current
- Yes
- Repository scan complete
- No
- Skill scan complete
- No
- Observed behavior
- Network or broad shell
- Last checked
- Nov 10, 2026
These are observations at the recorded commit, not a guarantee of safety. Review the source before running it.
Install this skill
Choose an agent in your Stack or copy a command below. Commands fetch the pinned commit and copy only this skill directory. Existing destinations are refused. Copying a command does not install anything.
An install command is unavailable: current rules, complete repository and skill scans, an eligible behavior level and a permitted license are required.
Repository context
- Repository stars (not skill ratings)
- 29,645
- Repository last updated
- Nov 11, 2026
- License
- MIT
Observed agent integration: gemini-cli
- agentic-ai Repository topic
- anthropic-claude Repository topic
- claude-ai Repository topic
- claude-code Repository topic
- claude-skills Repository topic
- claude-code-skills Repository topic
- ai-coding-agent Repository topic
- claude-code-plugins Repository topic
- developer-tools Repository topic
- openai-codex Repository topic
- engineering Derived category
Files and excerpt
File metadata and permitted, redacted excerpts come from the recorded scan. Source links are pinned to that commit.
Read excerpt
# /sprint-plan
Create a sprint plan for `$ARGUMENTS` with explicit capacity math, a carry-over check, and a definition-of-ready gate. The first token(s) of `$ARGUMENTS` are the sprint goal; a trailing number is treated as team capacity (story points or person-days). If no capacity is given, compute it in Phase 1 — never invent it.
## Usage
```bash
/sprint-plan <goal> [capacity]
# e.g. /sprint-plan "Checkout v2 ready for beta" 34
```
## Phase 1 — Capacity Math (do the arithmetic, show it)
1. **Raw capacity** = team size × working days in sprint × focus factor (default 0.7; ask if unknown)